Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Kenilworth
- Worksite Name
- A429 Kenilworth Road
- Contractor
- BBV JV
- Type of works
- Road closure
- Estimated Start Date
- 18/08/2025
- Estimated End Date
- 20/09/2025
What we are doing
We are in the final phase of delivering the realigned A429 Kenilworth Road and the new overbridge. We need to finish the embankments, reinstate and resurface the footpaths, position final utilities and complete the final highway drainage works.
To carry out the works in a safe and secure environment, we will need to install temporary traffic lights for one week. We will also need to close the road whilst we complete the works.
The temporary traffic lights will be in place from Monday 18 August to Tuesday 26 August 2025. We will then close the road from Tuesday 26 August to Saturday 20 September 2025. The traffic lights and road closure will both be 24 hours a day.
Access to properties will be maintained throughout, with access for pedestrians and cyclists.