Update: Notice of construction work

Work item: HS2-MW-BBVS-Ph1-OOC-St-S4-CR-42-09/05/2024

Work Item Summary

Project Phase
Phase 1
Region
Old Oak and North Acton
Location
Old Oak, Old Oak Common lane
Worksite Name
Old Oak Common
Contractor
BBVS JV
Type of works
Bridge protection works, Bridge works, Construction, Large load delivery/collections, Protection Works
Estimated Start Date
20/10/2024
Estimated End Date
16/12/2024

What we are doing

As we continue with the works at Old Oak Common Station, we need to undertake construction works near to the Central Line.

We need to do this work to support our infrastructure for the expansion of the Network Rail railway and for the new bridges. Our teams will deliver this work in two phases.

Phase 1 Permanent Works

We need to install five concrete supports behind the existing Central Line abutment. These will support the new bridge decks on the new railway bridges.

Phase 2 Temporary Works

Once we’ve completed the Phase 1 works, we will need to install a temporary retaining wall constructed from steel supports. This will support the Network Rail infrastructure.

Please see the link below for further information.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]