Work Item Summary
- Project Phase
- Phase 1
- Region
- Northamptonshire
- Location
- Thorpe Mandeville
- Worksite Name
- Banbury Lane
- Contractor
- EKFB JV
- Type of works
- Road closure
- Estimated Start Date
- 18/09/2025
- Estimated End Date
- 26/09/2025
What we are doing
Between Thorpe Mandeville and Culworth we have been building the Lower Thorpe viaduct. Earlier this summer, the Lower Thorpe viaduct was launched over Banbury Lane.
In order to complete the next phase of the works, the viaduct deck concrete slabs need to be installed.
Whilst we complete this activity above the road, to ensure the safety of road users, short closures of Banbury Lane are required. There will be daytime closures to erect scaffolding, followed by a full closure for the concrete works.
Download information relating to these works