Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Thorpe Mandeville
- Worksite Name
- Banbury Lane
- Contractor
- EKFB JV
- Type of works
- Concrete pours, Road closure
- Estimated Start Date
- 05/02/2026
- Estimated End Date
- 21/04/2026
What we are doing
We will be working on a platform above the road, constructing the deck of the viaduct using poured concrete and steel reinforcement.
Location
Banbury Lane, Thorpe Mandeville.
Duration
- Thursday 5 February to Friday 24 April 2026
Please note:
- These dates are subject to change dependent on the construction schedule and weather.
What to expect
Road closure on a section of Banbury Lane, Thorpe Mandeville.
HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]