Work Item Summary
- Project Phase
- Phase 1
- Region
- Northamptonshire
- Location
- Boddington
- Worksite Name
- Boddington road
- Contractor
- EKFB JV
- Type of works
- Road closure, Utility Works
- Estimated Start Date
- 09/02/2026
- Estimated End Date
- 05/06/2026
What we are doing
Construction of a new section of Boddington Road and complex utility works.
Location
Boddington Road, nr Boddington.
Duration
Monday 9 February 2026 for approximately 4 months.
What to expect
- The closure of Boddington Road, with a signed diversion in place.
- Workforce and machinery in the road.
HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]