Notice of road closure Cromwell Lane, Burton Green
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-UT-16-03/03/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire, West Midlands
- Location
- Burton Green
- Worksite Name
- Cromwell Lane
- Contractor
- BBV JV
- Type of works
- Gas pipeline diversion, Road closure, Traffic management
- Estimated Start Date
- 14/06/2022
- Estimated End Date
- 20/08/2022
What we are doing
Gas diversion works Cromwell Lane, Burton Green.
In order to undertake gas and sewer diversion works, we will be closing Cromwell Lane between Red Lane and Hodgetts Lane.
These works will be taking place in three phases between Tuesday 14 June 2022 and Saturday 20 August 2022.
- Phase one; Will be an off-peak closure from 9.30am to 3pm from Tuesday 14 June to Friday 17 June.
- Phase two; Will be a full closure 24 hours a day 7 days a week from Monday 20 June to Friday 1 July.
- Phase three: This phase was originally programmed between Monday 25 July and Saturday 20 August, however due to circumstances beyond our control this will now be a full closure 24 hours a day seven days a week from Monday 1 August to Wednesday 24 August.
We apologise for any additional inconvenience this delay may cause.
Our working hours will be 8am to 6pm on weekdays and 8am to 1pm on Saturdays.
Pedestrian access on Cromwell Lane will be maintained at all times. A fully signposted diversion will be in place throughout the closures and access to all properties will be maintained.
Our workforce maybe on site one hour before and one hour after to set up and secure our equipment.
Download information relating to these works
- Notice of road closure Cromwell Lane, Burton Green
- Notice of road closure Cromwell Lane, Burton Green Amended
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]