Notice of Road Closure, Dalehouse Lane, Kenilworth.

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-9-15/09/2022

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire, West Midlands
Location
Kenilworth
Worksite Name
Dalehouse Lane
Contractor
BBV JV
Type of works
Road closure
Estimated Start Date
21/10/2022
Estimated End Date
22/10/2022

What we are doing

To facilitate plant crossing, we will be carrying out line marking works for a speed limit reduction on Dalehouse Lane, Kenilworth.
A section of Dalehouse Lane will be temporarily closed, to ensure a safe working area while line marking is carried out. The lane will be reopened once the works are completed.
For the safe operation of the plant crossing, the speed limit on Dalehouse Lane will be reduced from 50mph to 30mph until Spring 2024.
Dalehouse Lane will be closed on 21 October 2022 between 9.30am and 3.30pm and 22 October 2022 8am to 1pm if required, to minimize disruption to peak traffic. A full diversion will be in place. Access will be maintained to all properties.
Our workforce maybe on site one hour before and one hour after to set up and secure our equipment.