Notice of road closure for utility works on Hunningham Road

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-23-21/06/2024

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire
Location
Offchurch
Contractor
BBV JV
Type of works
Road closure
Estimated Start Date
31/07/2024
Estimated End Date
13/09/2024

What we are doing

To progress the construction of Hunningham Road Overbridge we will be carrying out a utility diversion along Hunningham Road. The utility diversion works will be completed in four phases. During these phases we will complete surveys to locate the existing utility services and assess ground conditions. This will be followed by the digging of trenches, installing cables and completing connections and testing.

These works will involve our teams operating in the carriageway. To ensure the safety of our workforce and the public we will install the following road closures:
Phase one: 31 July – 6pm – 10pm, full closure for one evening.
Phase two: 19 August to13 September – full road closure.
Phase three: 21 October to 8 November – full road closure.
Phase four: 16 December to 20 December – off peak full closure between 8am – 6pm.