UPDATED – Notice of road closure on Gilson Drive – NGED connections

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-06/08/2024

Work Item Summary

Project Phase
Phase 1
Region
Birmingham, West Midlands
Location
Gilson
Worksite Name
Gilson Drive
Contractor
BBV JV, National Grid Electricity Distribution (NGED)
Type of works
Road closure
Estimated Start Date
11/11/2024
Estimated End Date
29/11/2024

What we are doing

To continue for our preparation of the HS2 railway we will be completing works on Gilson Drive by installing traffic management to complete NGED connections and reinstatement works.

Update: Due to changes in the works program and to complete the works safely, the Gilson Drive road closure will now be in place each weekday from Wednesday 13 November to Friday 29 November. The closure will be in place from 7:30am to 17:30pm each day.

Access will be maintained to residents and deliveries using traffic management marshals.

 