Notice of road closure on Moor Lane, Newlands Lane and Jonghams Lane, Stockwell Heath

Work item: HS2-EW-KIER-Ph2a-Ar-CA01-Surv-04-7/1/2022

Work Item Summary

Project Phase
Phase 2a
Region
West Midlands
Location
Stockwell Heath
Worksite Name
Moor Lane
Contractor
Kier
Type of works
Survey
Estimated Start Date
27/01/2022
Estimated End Date
04/02/2022

What we are doing

We will be carrying out ground penetrating surveys to help us identify the location of buried utility services, such as gas, electric or water. These surveys are non-intrusive, we will use a machine that transmits an electromagnetic pulse into the ground. These pulses reflect off features in the ground, allowing us to collect data and to understand the depth of the buried utility services.
Along with ground penetrating surveys, we will carry out several other surveys. For the safety of both our workforce and motorists, we will have to close Moor Lane and Jonghams Lane.

When the work will take place

The closures will take place between Thursday 27 January to Friday 4 February 2022 excluding weekends. Please note that all our planned roadworks may be subject to change due to weather conditions or unforeseen circumstances. We will notify you in advance of any changes.

How this will affect your journey

On Thursday 27 January to Friday 28 January from 9am to 4pm we will need to close Jonghams Lane so to undertake our work safely. During the road closure, we will maintain access to and from properties on Jonghams Lane.

On Thursday 27 January to Friday 4 February (excluding weekends) from 9am to 4pm we will need to close Moor Lane and some of Newlands Lane to undertake our work safely.