Notice of road closure on Park Lane, Huddlesford

Work item: HS2-MW-BBV-Ph1-Ar-No-N2-Traf-7-12/09/2022

Work Item Summary

Project Phase
Phase 1
Region
Staffordshire, West Midlands
Location
Huddlesford
Contractor
BBV JV
Type of works
Construction, Road closure, Traffic management
Estimated Start Date
24/10/2022
Estimated End Date
14/11/2022

What we are doing

We will be undertaking work along Park Lane from Monday 24 October. The work includes, vegetation clearance, installing security fencing and signage, constructing of our haul road and creating a safe work zone for our works access off Park Lane.

The works will take place from Monday 24 October. To carry out our works safely, we will install a road closure of Park Lane for one week. The road closure will be in place between the hours of 9:30am to 3:30pm each day. Following the week closure, we will install temporary traffic lights at the same location for two weeks. This will start from Monday 31 October and will be in place 8am to 5pm each day.