Update-Notice of Road Closure on Station Road North, Quainton
Work item: HS2-EKFB-25-1139
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Station Road
- Worksite Name
- Station Road
- Contractor
- EKFB JV
- Type of works
- Road closure
- Estimated Start Date
- 28/04/2025
- Estimated End Date
- 01/09/2025
What we are doing
From the end of April, a section of Station Road North will be closed.This is to allow the construction of the eastern tie-in which will connect the new Station Road alignment into the old road. Works will include removing the old road surface, forming the new alignment to include an access road to service properties, completing drainage works, installing new curb stones, road resurfacing and white lining. Individual discussions are taking place with residents affected by the closure to agree access requirements.
Works on the new Station Road alignment will continue offline and the road will be completed and open to traffic in the spring of 2026.
This is for reasons of safety, as our operatives will be working on and around the carriageway.
From 28 April 2025 until 1 September 2025 a section of Station Road North will be closed with signed diversion routes in place.
These dates may change due to conditions outside of our control, such as weather. Please refer to the HS2 website regularly to check for any changes and updates.