Notice of road closure, Radstone Road, Radstone January 2026 update

Work item: HS2-EKFB-26-1635

Work Item Summary

Project Phase
Phase 1
Region
Northamptonshire
Location
Radstone
Worksite Name
Radstone
Contractor
EKFB JV
Type of works
Road closure
Estimated Start Date
03/11/2025
Estimated End Date
30/03/2026

What we are doing

Further to our December update, we are continuing works to complete the overbridge and finalise the new road alignment.

This includes delivering the necessary improvements highlighted through our road safety audits, as well as undertaking some adjustment works at the western tie-in.

Location

Radstone Road, Radstone.

Duration

We are actively working towards achieving an opening by the end of March 2026.

What to expect

A full road closure 24 hours a day on a section of Radstone Road between Brackley and Helmdon. The road remains open on the old alignment for pedestrians and cyclists, however we ask cyclists to dismount when travelling through the works area.

HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.