Skip to main page content
View route map

Notice of road closure, Radstone Road, Radstone March 2026 UPDATE

Work item: HS2-EKFB-26-1635

Work Item Summary

Project Phase
Phase 1
Region
Northamptonshire
Location
Radstone
Worksite Name
Radstone
Contractor
EKFB JV
Type of works
Road closure
Estimated Start Date
03/11/2025
Estimated End Date
30/04/2026

What we are doing

Further to our January update, we are continuing works to complete the overbridge and finalise the new road alignment.

This includes delivering the necessary improvements highlighted through our road safety audits, as well as undertaking some adjustment works at the western tie-in.

For further information from the engagement team, we are holding a drop in on:

11 March between 1-4pm at Helmdon village hall, 20 Church Street Helmdon Northamptonshire NN13 5QJ

Location

Radstone Road, Radstone.

Duration

We would like to update you on the current closure. To complete the final remedial works, the road closure has been extended until mid-April 2026.

What to expect

A full road closure 24 hours a day on a section of Radstone Road between Brackley and Helmdon.

The road remains open on the old alignment for pedestrians and cyclists, however we ask cyclists to dismount when travelling through the works area.

HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]