Notice of road closure, Rocky Lane, Wendover
Work item: HS2-MW-EK-Ph1-Ar-Ce-C1-Traf-30-07/10/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Rocky Lane, Wendover
- Contractor
- EKFB JV
- Estimated Start Date
- 21/10/2024
- Estimated End Date
- 22/10/2024
What we are doing
In October, we will be carrying out water main works on Rocky Lane. In preparation for our works on the Rocky Lane underbridge, we will be required to excavate trial holes, record findings and test soil within the carriageway. These works will take place across two days on Rocky Lane. As we need to protect the safety of our team working close to the carriageway, the road will be closed for the duration of our works.
From Monday 21 October (9:00am) – Tuesday 22 October (5:00pm) to minimise disruption, we will introduce a fully signposted diversion route.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]