Notice of road closure Rugby Road, Cubbington

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-15-11/07/2022

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire, West Midlands
Location
Cubbington
Worksite Name
Rugby Road
Contractor
BBV JV
Type of works
Road closure, Survey, Utility works / surveys
Estimated Start Date
11/07/2022
Estimated End Date
15/07/2022

What we are doing

Notice of road closure Rugby Road, Cubbington

To facilitate the building of the railway it will be necessary to divert the existing BT cables on Rugby Road.
To allow us to carry out these works safely Rugby Road will be closed from Monday 11 July to Friday 15 July. The closure will be in place off-peak from 9.30am to 3.30pm each day. Our workforce maybe on site one hour before and one hour after to set up and secure our equipment.
A fully signed diversion will be in place throughout this closure. Access will be maintained to all properties while these works are being carried out.