Notice of Road Closure, Shipton Lee Road, Quainton

Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-47-11/02/2025

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Quainton
Contractor
EKFB JV
Type of works
Road closure
Estimated Start Date
05/03/2025
Estimated End Date
06/03/2025

What we are doing

In early March 2025 we will be closing a section of Shipton Lee Road to carry out tree surveys and general verge works. To carry out these works safely and effectively we will need to put in place a road closure with signed diversions. Our teams will be working in open trenches on and around carriageway.

The closure will be from 8.30am to 5.30pm, from Wednesday 5 March until Thursday 6 March 2025.