Updated Notice of Road Closure, Station Road South, Quainton, Buckinghamshire

Work item: HS2-EKFB-25-1222

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Quainton
Worksite Name
Station Road South
Contractor
EKFB JV
Type of works
Road closure
Estimated Start Date
20/10/2025
Estimated End Date
30/06/2026

What we are doing

We are constructing the western tie-in to the new Station Road alignment.

Location

Station Road South, Quainton, Buckinghamshire

Duration

Until 30 June 2026

What to expect

A section of Station Road South will be closed with varied activities with both quiet and busier periods. Station Road bridge will remain closed until this realignment is complete and open to traffic

HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]