Notice of Road Closure – Truggist Lane Balsall Common

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-15-12/08/2024

Work Item Summary

Project Phase
Phase 1
Region
Solihull
Location
Balsall Common
Worksite Name
Truggist Lane
Contractor
BBV JV
Type of works
Road closure
Estimated Start Date
02/09/2024
Estimated End Date
05/09/2024

What we are doing

The new railway will pass over Truggist Lane on a viaduct structure. To protect the road during construction sheet piles will need to be driven into the verges on either side of the road. Sheet piling can be loud and disruptive.

To minimise this disruption, we plan to pre-auger the existing ground which will significantly reduce the noise levels. To do this safely we will need to close the road from 9:30am until 3:30pm for 4 days from Monday 2 September until Thursday 5 September.

A fully signed diversion will be in place for the duration of our works.

Download information relating to these works

Find out more about