Work Item Summary
- Project Phase
- Phase 1
- Region
- Solihull
- Location
- Balsall Common
- Worksite Name
- Truggist Lane
- Contractor
- BBV JV
- Type of works
- Road closure
- Estimated Start Date
- 02/09/2024
- Estimated End Date
- 05/09/2024
What we are doing
The new railway will pass over Truggist Lane on a viaduct structure. To protect the road during construction sheet piles will need to be driven into the verges on either side of the road. Sheet piling can be loud and disruptive.
To minimise this disruption, we plan to pre-auger the existing ground which will significantly reduce the noise levels. To do this safely we will need to close the road from 9:30am until 3:30pm for 4 days from Monday 2 September until Thursday 5 September.
A fully signed diversion will be in place for the duration of our works.