What we are doing
BBV will be carrying out work to construct a plant crossing on Truggist Lane near to the low bridge Berkswell Station. This will involve a section of the old road being replaced with a reinforced concrete slab to take the weight of heavy machinery crossing the lane. Enabling works contractor LMJV will also be carrying out vegetation clearance in the area to prepare for future construction works.
Due to unforeseen circumstances works are now scheduled to start on 9 August 2021 and run through to the 11 September 2021. These works are subject to weather conditions. To carry out this work safely the road will be fully closed during this period for motor vehicles but pedestrian access will be maintained throughout the closure.