Notice of Road Closure – Waste Lane
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-6-27/8/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Solihull
- Location
- Solihull
- Worksite Name
- Waste Lane
- Contractor
- BBV JV
- Type of works
- Road closure
- Estimated Start Date
- 20/01/2025
- Estimated End Date
- 24/01/2025
What we are doing
To enable the new railway to pass under Waste Lane, the road will have to be realigned over a new bridge slightly to the north of the existing bridge.
The construction of the bridge structure is well underway and is being built ‘off-line’. Where the new road alignment ties in with the existing road a number of tree stumps will need to be removed. In order to do this the vacuum excavator and the stump grinder will need to utilise the road space and the road will have to be closed.
We will close the road on 20 January for five days at off peak times only from 9:30am until 3:30pm.