Notice of road closures, A41 realignment

Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-Traf-34-16/08/2024

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
A41, Waddesdon
Contractor
EKFB JV
Type of works
Overnight road closure, Road closure
Estimated Start Date
06/09/2024
Estimated End Date
07/10/2024

What we are doing

In September, we will be completing the second phase of our A41 realignment works to connect the road to the newly built roundabout near Waddesdon.

Prior to the realignment works, we will be undertaking utility works on a section of the A41 around Fleet Marston, between Waddesdon and Aylesbury. To carry out these works safely and effectively, the road will be closed for three consecutive nights. This is for reasons of safety, as our operatives will be working on and around the carriageway.

For our realignment works, the road will be closed between Waddesdon Hill and Waddesdon for 24 hours on three weekends in September, with one contingency weekend in October.

Access to properties along the A41 will be maintained throughout all closures.
When will these works take place?

  • Overnight road closures:
    • Friday 6 September – Monday 9 September, 8:30pm – 5:30am
  • 24-hour road closures:
    • Friday 13 September 8:30pm – Monday 16 September 5:30am
    • Friday 20 September 8:30pm – Monday 23 September 5:30am
    • Friday 27 September 8:30pm – Monday 30 September 5:30am
    • Friday 4 October 8:30pm – Monday 7 October 5:30am
      (contingency weekend)