Notice of road closures, Chetwode

Work item: HS2-MW-EK-Ph1-Ar-Ce-C1-Traf-16-11/07/2024

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Chetwode
Contractor
EKFB JV
Type of works
Road closure, Vegetation clearance
Estimated Start Date
04/11/2024
Estimated End Date
20/12/2024

What we are doing

This autumn, we will be carrying out works along School End, Chetwode Grange Road, Main Street and Preston Bissett Road.

We will be carrying out survey activities and clearing some localised areas of vegetation. These works will facilitate the continued construction of the main structures we are building in the area. For reasons of safety and due to the narrow width of the roads, these works will require some road closures.
Our teams will also continue carrying out utility works and duct installation for the permanent road realignment of the junction of Main Street and Preston Bissett Road. We will continue to update communities as our works progress.

A section of School End will be closed during the day between the hours of 8.30am-5.30pm on the following dates:
• Monday 4 November to Friday 8 November
• Monday 18 November to Friday 22 November

A section of School End will be close 24-hours a day on the following dates:
• Tuesday 10 December to Saturday 15 December
• Tuesday 17 December to Friday 20 December

A section of Main Street will close 24-hours a day, for works on the following dates:
• Monday 25 November to Friday 20 December