Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Worksite Name
- Chetwode
- Contractor
- EKFB JV
- Type of works
- Road closure
- Estimated Start Date
- 30/06/2025
- Estimated End Date
- 29/08/2025
What we are doing
We’re continuing with our works on School End in Chetwode. Works include utility installations, carriageway removal and temporary surface installation. Towards the end of this phase of closures we will be installing pavements and road markings. Due to a limited safe-working area, a series of road closures are necessary.We’ll keep our community updated on these developments.
A section of School End will be closed 24 hours a day, for works on the following dates:
• Monday 30 June to Friday 18 July 2025
• Monday 28 July to 01 August 2025
• Monday 11 August to Wednesday 13 August 2025
• Monday 18 August to Friday 29 August 2025.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]