Notice of Severn Trent Construction Works – Erskine Street

Work item: HS2-EW-UT-Ph1-Ar-No-N1-UT-47-24/03/2022

Work Item Summary

Project Phase
Phase 1
Region
Birmingham, West Midlands
Location
Birmingham, Erskine Street
Worksite Name
Erskine Street
Contractor
Severn Trent Water
Type of works
Excavation works, Traffic management
Estimated Start Date
18/04/2022
Estimated End Date
27/05/2022

What we are doing

Severn Trent need to carry out work in Erskine Street on their assets. The work will include excavating across the bottom of Erskine Street into Inkerman Street. Once the work is complete reinstatement of the highway will take place and the lane closure will be removed. In order to undertake the work safely a two-phase traffic management set up will be installed. Phase 1 will be from 18 April 2022 until 6 May 2022 and Phase 2 will be from 6 May 2022 until 27 May 2022. A further day of testing will be carried out on 13 June 2022. The traffic management set up will ensure access is still maintained to Villamead Ltd and Mid-Fab.

How will this impact you?
Severn Trent will be working in the area highlighted red on the image, there will be clearly signed lane closures and working areas.
All activity will take place in a securely fenced-off area and you may see an increase in construction traffic during the works.
Severn Trent has a responsibility for delivering water and sewerage services to homes and businesses across the region, and to ensure that the impact of any work is kept to a minimum.