Notice of site activity during the Queen’s Platinum Jubilee week – Showing location for West Ruislip Portal

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-works-1-20/05/22

Work Item Summary

Project Phase
Phase 1
Region
Hillingdon
Location
Newyears Green Lane
Worksite Name
Copthall, West Ruislip
Contractor
SCS JV
Type of works
Cement pours, Excavation works, Steel fixing work, TBM Associated Works
Estimated Start Date
02/06/2022
Estimated End Date
04/06/2022

What we are doing

What we are doing
We wrote to you recently to update you about our ongoing works at our sites on Harvil Road and New Years Green Lane.

We wanted to let you know that these works will continue throughout the Queen’s Platinum Jubilee week. We will be carrying out works at our site compounds at:

Copthall tunnel site and Northern Sustainable Placement area
From 2 to 4 June 2022, between 8am and 5pm work will be ongoing at our sites on Harvil Road and Newyears Green Lane. We will be carrying out steel fixing work, excavation and moving material. The conveyor system will be in operation during this time.

West Ruislip portal site
24/7 assembly works for the tunnel boring machine will continue. These works will include steel fixing and a concrete pour, lifting operations and starting the TBM assembly into the launch chamber area.

The works we will carry out on these dates will be limited to the activities mentioned above and are confined within our sites.

We would like to apologise in advance for working over the bank holiday period and for any inconvenience this may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way.

We will ensure that disruption is kept to a minimum.