Notice of spray applied water proofing system at Old Oak Common
Work item: HS2-MW-BBVS-Ph1-OOC-St-S4-prog-works-44-25/07/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Old Oak and North Acton
- Location
- Old Oak Common lane
- Worksite Name
- Old Oak Common
- Contractor
- BBVS JV
- Type of works
- Construction
- Estimated Start Date
- 11/08/2022
- Estimated End Date
- 19/08/2022
What we are doing
Spray applied waterproofing system
On the dates 11, 12, 18 and 19 August, we will be carrying out some waterproofing works. This activity involves spraying a waterproofing product onto the reinforced concrete structure to protect from water damage, such as leaks, and ensuring longevity of the station.
This activity will take place within the confines of the HS2 Station Box in the Stamford Brook Sewer and the ground floor slab towards the East of the site. Please see the map on Page 2 for the location of these works.
On the 11 and 12 August, this activity will take place within the confines of the HS2 Station Box Stamford Brook Sewer and on the 18 and 19 August, it will take place at the East Box site. These works will take place during the normal working hours of 8am – 6pm.
The waterproofing product is not toxic; however, it has a distinctive smell during application. This smell typically disappears once cured approx. 2 hours after application.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]