Work item: HS2-MW-BBVS-Ph1-OOC-St-S4-prog-works-44-25/07/2022

Work Item Summary

Project Phase
Phase 1
Region
Old Oak and North Acton
Location
Old Oak Common lane
Worksite Name
Old Oak Common
Contractor
BBVS JV
Type of works
Construction
Estimated Start Date
11/08/2022
Estimated End Date
19/08/2022

What we are doing

Spray applied waterproofing system

On the dates 11, 12, 18 and 19 August, we will be carrying out some waterproofing works. This activity involves spraying a waterproofing product onto the reinforced concrete structure to protect from water damage, such as leaks, and ensuring longevity of the station.

This activity will take place within the confines of the HS2 Station Box in the Stamford Brook Sewer and the ground floor slab towards the East of the site. Please see the map on Page 2 for the location of these works.

On the 11 and 12 August, this activity will take place within the confines of the HS2 Station Box Stamford Brook Sewer and on the 18 and 19 August, it will take place at the East Box site. These works will take place during the normal working hours of 8am – 6pm.

The waterproofing product is not toxic; however, it has a distinctive smell during application. This smell typically disappears once cured approx. 2 hours after application.