Notice of Stamford Brook Sewer Backfilling Works

Work item: HS2-MW-BBVS-Ph1-OOC-So-S1-prog-works-8-23/02/2023

Work Item Summary

Project Phase
Phase 1
Region
Old Oak and North Acton
Location
Old Oak Common
Worksite Name
Old Oak Common
Contractor
BBVS JV
Type of works
Utility works / surveys
Estimated Start Date
12/06/2023
Estimated End Date
12/07/2023

What we are doing

Works to the redundant part of the Stamford Brook Sewer
We wrote to you in March to let you know that the newly diverted Stamford Brook Sewer works have completed, and the sewer is operational.

The Stamford Brook Sewer passes under the Great Western Railway tracks and into the HS2 Old Oak Common Station.

Before the digging of the new HS2 platforms could start, a section of the Stamford Brook Sewer pipe had to be diverted away from the below ground platforms location.

We now need to backfill the old, redundant sewer with foam concrete. These works are taking place underground and will remove the risk of the redundant sewer collapsing at a later date.

These works are taking place inside the HS2 Old Oak Common Station site in the approximate location shown on the map on page two.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]