Notice of start of main works in Saltley
Work item: HS2-EW-BBV-Ph1-Ar-No-N1-Traf-21-10/02/2020
Work Item Summary
- Project Phase
- Phase 1
- Region
- Birmingham, West Midlands
- Location
- Saltley
- Contractor
- BBV JV
- Type of works
- Construction
- Estimated Start Date
- 05/10/2020
- Estimated End Date
- 31/05/2021
What we are doing
Site setup
Site setup will start in Saltley in late October 2020. As work sites are set up hoarding will be erected to protect members of the public from the construction work. Haul roads will also be created as the sites are setup.
Haul roads are temporary roads provided within a working area to allow for the movement of construction materials, construction machinery and/or construction staff around the site.
Haul roads are Balfour Beatty Vinci’s preferred logistical transport link, as they reduce the number of vehicle movements interfering with the existing local road network and provide the greatest possible control over works activity.
During site setup residents may hear low levels of construction noise and see deliveries of materials and equipment.