Notice of survey work on Moor Lane, B5013, Newlands Lane and Hollow Lane
Work item: HS2-EW-KIER-Ph2a-Ar-CA01-Surv-09-22/2/2022
Work Item Summary
- Project Phase
- Phase 2a
- Region
- Staffordshire
- Location
- B5013, Hollow Lane, Moor Lane, Newlands Lane
- Worksite Name
- B5013, Hollow Lane, Moor Lane, Newlands Lane
- Contractor
- Kier
- Type of works
- Ground investigations, Survey
- Estimated Start Date
- 28/03/2022
- Estimated End Date
- 08/04/2022
What we are doing
We will be carrying out ground penetrating surveys to help us identify the location of buried utility services, such as gas, electric or water. These surveys are non-intrusive, we will use a machine that transmits an electromagnetic pulse into the ground. These pulses reflect off features in the ground, allowing us to collect data and to understand the depth of the buried utility services.
Along with ground penetrating surveys, we will carry out several other surveys. To carry these out safely, we will need to close Moor Lane, Newland Lane, and Hollow Lane, and install temporary traffic lights on the B5013.
When the work will take place
Work will take place from Monday 28 March to Friday 8 April 2022. Please note that all our planned roadworks may be subject to change due to weather conditions or unforeseen circumstances. We will notify you in advance of any changes.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]