Notice of survey work on the A51 between Main Road and Hoomill Lane

Work item: HS2-EW-KIER-Ph2a-Ar-CA02-Surv-09-16/11/2021

Work Item Summary

Project Phase
Phase 2a
Region
Staffordshire
Location
Great Haywood
Worksite Name
Hoomill lane
Contractor
Kier
Type of works
Survey
Estimated Start Date
16/05/2022
Estimated End Date
27/05/2022

What we are doing

We will be carrying out ground penetrating surveys to help us identify the location of buried utility services, such as gas, electric or water. These surveys are non-intrusive, we will use a machine that transmits an electromagnetic pulse into the ground. These pulses reflect off features in the ground, allowing us to collect data and to understand the depth of the buried utility services.
Along with ground penetrating surveys, we will carry out several other surveys. For the safety of both our workforce and motorists, we need to install overnight temporary traffic lights on the A51 between Main Road and Hoomill Lane.

When the work will take place

The ground penetrating survey and topographical surveys will take place on Monday 16 May and Friday 27 May 2022.