Notice of survey works at Hanchurch Interchange (M6 junction 15/A500)

Work item: HS2-EW-BBV-Ph2a-Ar-So-S4-Prog-works-15-20/01/2022

Work Item Summary

Project Phase
Phase 2a
Region
Staffordshire
Location
Hanchurch Interchange (M6 junction 15/A500)
Worksite Name
Hanchurch Interchange, Junction 15
Contractor
Balfour Beatty
Type of works
Ground investigations
Estimated Start Date
06/02/2022
Estimated End Date
20/03/2022

What we are doing

What we are planning

Last year, we carried out Ground Investigation surveys to help us understand the ground conditions to help inform the design of the junction. While carrying out the work, we encountered some challenging ground conditions. As a result, we were unable to gather all the data needed. Therefore, we need to return to carry out some further surveys. From 6 February 2022, we will need to work in the highway around Hanchurch Interchange, Newcastle Road and Whitmore Road junction. This will include six Sunday daytime shifts (8am to 4pm) and fifteen night shifts (8pm to 6am).

How will this affect you?

As with previous works, we expect there to be some delays to traffic, particularly on the Sunday shifts. We will open traffic routes early if we make good time with our works. The surveys will also generate some noise. Where work is close to houses, we will work on Sunday during the day rather than the night. We will maintain residents’ access to their properties at all times. When the closures are in front your property, please you get the attention of our traffic management team who will be on site. They will facilitate your safe passage through our working area.