Notice of surveys and ground investigation works

Work item: HS2-EW-BBV-Ph1-Ar-No-N1-Traf-6-21/04/2021

Work Item Summary

Project Phase
Phase 1
Region
Old Oak and North Acton
Location
Old Oak
Contractor
BBVS JV
Type of works
Ground investigations
Estimated Start Date
02/05/2021
Estimated End Date
23/07/2021

What we are doing

From 18 April the Great Western main line will be closed for the de-commissioning of the Heathrow Express depot. These works will include de-wiring and track recovery and will last for several weeks.

We previously notified yu that while this line is closed, work would start on 25 April. This work will now start on the 2 May. We will carry out important surveys and ground investigation work adjacent to the railway.