Notice of Surveys on the A525 Newcastle Road

Work item: HS2-EW-Kier-Ph2a-Ar-CA04-Prog-works-31-14/12/2022

Work Item Summary

Project Phase
Phase 2a
Region
Staffordshire
Location
Newcastle Road
Worksite Name
A525, Newcastle Road
Contractor
Kier
Type of works
Topographical surveys, Traffic management
Estimated Start Date
09/01/2023
Estimated End Date
17/02/2023

What we are doing

We have carried out ground penetrating radar and topographical surveys which are above ground. Our next step is to do further surveys to help us inform future construction design. This work involves pavement coring, bore holes, trial pits on and off the highway. We will excavate below ground to provide us with samples and allow us to view the structure and record the layout of land.

To carry out this work safely we will need temporary traffic lights during the day and night closures on the A525 Newcastle road between the A51 carriageway and Manor Road heading towards Madeley. The traffic management will only be required when our work is being carried out otherwise the road will remain open, and the traffic management will be removed from site.

When the work will take place

These works will now take place from Monday 9 January to Friday 17 February 2023. Please note that all our planned roadworks may be subject to change due to weather conditions or unforeseen circumstances.

We will work on Monday 9 January to Friday 17 February 2023 with a full road closure on the A525 Newcastle Road up to Manor Road during the night from 7pm to 5am.

We will work on Monday 9 January to Friday 17 February 2023 with temporary traffic lights on the A525 between Back Lane and Manor Road during the day from 8am to 5pm.