Notice of surveys on Yarnfield Lane

Work item: HS2-EW-KIER-Ph2a-Ar-CA03-Surv-11-12/12/2021

Work Item Summary

Project Phase
Phase 2a
Region
West Midlands
Location
Yarnfield
Worksite Name
Yarnfield
Contractor
Kier
Type of works
Survey
Estimated Start Date
04/01/2022
Estimated End Date
10/01/2022

What we are doing

We will be carrying out ground penetrating surveys to help us identify the location of buried utility services, such as gas, electric or water. These surveys are non-intrusive, we will use a machine that transmits an electromagnetic pulse into the ground. These pulses reflect off features in the ground, allowing us to collect data and to understand the depth of the buried utility services.

Along with ground penetrating surveys, we will carry out several other surveys. For the safety of both our workforce and motorists, we will put temporary 2-way traffic lights on Yarnfield Lane while we carry out the work between Moss Lane and the M6 overbridge.

When the work will take place

The ground penetrating survey and topographical surveys will take place on Tuesday 4 January to Monday 10 January 2022. Please note that all our planned roadwork may be subject to change due to weather conditions or unforeseen circumstances.

How this will affect your journey

On Tuesday 4 January to Monday 10 January (excluding weekends) from 9am to 5pm we need to install temporary 2-way traffic lights. These will be located on the Yarnfield Lane and will differ each day as we move along the carriageway. During these times, journeys make take longer than usual.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]