Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-21-14/05/2025
Work Item Summary
- Project Phase
- Phase 1
- Region
- Solihull
- Location
- A452
- Worksite Name
- A452 Chester Road
- Contractor
- BBV JV
- Type of works
- Overnight road closure
- Estimated Start Date
- 02/06/2025
- Estimated End Date
- 02/06/2025
What we are doing
As we progress construction of the M42 motorway box structure we need undertake some upgrades to our A452 Chester Road compound access and install a safety barrier.
To safely carry out our works the following overnight closures are required:
A452 Chester Road:
Monday 2 June 2025 between 8pm to 6am.
We have booked a contingency closure if we are unable to complete the works during this closure.
The contingency overnight closure, if required, will be Tuesday 3 June 2025 between 8pm and 6am.
Birmingham Business Park access:
Access to Birmingham Business Park will be via Bickenhill Parkway
during these overnight closures.