Notice of temporary closure of Cappers Lane, Lichfield
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-05-09/01/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Staffordshire, West Midlands
- Location
- Lichfield
- Contractor
- BBV JV
- Type of works
- Excavated material deliveries, Road closure
- Estimated Start Date
- 03/06/2024
- Estimated End Date
- 30/09/2024
What we are doing
We will be constructing an access to our working area and completing surveys along Cappers Lane. We will undertake vegetation management at this location while constructing the access. We will also complete utility surveys that will require small excavations to establish where utilities and services are located beneath the road surface.
From the 3 June to 30 September 2024, we will be delivering earthwork material that will be stockpiled at our Cappers Lane compound. The deliveries of materials to our site will be from 8am-6pm.
In addition we will require a closure of a section of Cappers Lane from 3 June to 7 June 2024. The road will be closed from 9:30 am to 3:30 pm.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]