Notice of temporary closure of Lavender Hall Lane
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-46-01/04/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Solihull, West Midlands
- Location
- Berkswell
- Worksite Name
- Baulk Lane, Lavender Hall Lane
- Contractor
- BBV JV
- Type of works
- Gas pipeline diversion, Road closure
- Estimated Start Date
- 03/10/2022
- Estimated End Date
- 28/10/2022
What we are doing
Installation of temporary gas pipe.
UPDATE- Due to an ecological concern, these works originally scheduled to start on Monday 27 June have been rescheduled and will now commence on Monday 3 October 2022.
Due to the future realignment of Lavender Hall Lane, it will be necessary for us to install a temporary gas pipe under the road. For us to carry out this works safely, we need put in place a temporary closure of Lavender Hall Lane.
For safety reasons and at the request of SMBC it will also be necessary for us to close Baulk Lane, this is due to Baulk Lane not being suitable for 2-way traffic.
The Baulk Lane closure is for motor vehicles only and will remain open for pedestrians, cyclists, and horse riders.
Access to all properties will be maintained at all times.
The closures will be in place from Monday the 3 October 2022 until Friday 28 October 2022 for 24 hours a day including weekends.
Our working hours will be Monday to Friday 8am to 6pm and Saturday 8am to 1pm. Our workforce may be in place one hour before and one hour after to set up and secure our equipment.
A fully signed diversion will in place. These works are subject to weather conditions.
Download information relating to these works
- Notice of temporary closure of Lavender Hall Lane
- Updated notice of temporary closure of Lavender Hall Lane
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]