Updated – Notice of temporary closure of Netherstowe Lane
Work item: HS2-MW-BBV-Ph1-Ar-No-N2-Traf-7-16/01/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Staffordshire
- Location
- Netherstowe
- Contractor
- BBV JV
- Type of works
- Road closure
- Estimated Start Date
- 06/03/2023
- Estimated End Date
- 31/03/2023
What we are doing
*Update*
We will be diverting underground utilities, along Netherstowe Lane and Wood End Lane, as we build the new railway. We will commence the first phase of the diversion on Netherstowe Lane, which will require the carriageway to be excavated and works completed in the verges. To ensure the safety of the public, cyclists and equestrians we will install a temporary closure of Netherstowe Lane. These works will take place between Monday 06 March to Friday 31 March 2023. The closure will be in place between Monday and Friday each week for 24 hours a day. Our working hours will be from 8am to 6pm (Mon to Fri).
The closure will remain in place over the weekends to ensure the safety of the passing public.
Access to properties and emergency services will be maintained via the Lichfield Road entrance to Netherstowe Lane. See the attached notification detailing our road closure and the approved diversion route for road users.
We will also clearly signpost a local diversion route for cyclists.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]