Notice of temporary closure of Rookery Lane
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-Works-9-23/08/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Staffordshire
- Location
- Hints
- Contractor
- BBV JV
- Type of works
- Haul road construction
- Estimated Start Date
- 07/11/2022
- Estimated End Date
- 25/11/2022
What we are doing
Updated Information
The end date has been extended until 2 December.
We are constructing haul roads and accesses along the HS2 route. Haul roads are temporary roads provided within a working area to allow for the movement of construction materials, construction machinery and/or construction staff around the site. Haul roads are Balfour Beatty VINCI’s preferred logistical transport link, as they reduce the number of vehicle movements interfering with the existing local road network and provide the greatest possible control over works activity.
To allow our vehicles to safely cross Rookery Lane and to maintain the safety of road users, equestrian and pedestrians, we will create a signalised vehicle crossing point.
To enable us to complete these works, we will require a temporary closure of Rookery Lane over this period. These works will take place from 7 November to 18 November 2022. The closure will be in place for 24 hours each day until completion of the works.