Notice of temporary closure of Shaw Lane, Hanch
Work item: HS2-MW-BBV-Ph1-Ar-No-N2-Traf-6-16/12/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Staffordshire, West Midlands
- Location
- Hanch
- Worksite Name
- Shaw Lane
- Contractor
- BBV JV
- Type of works
- Road closure, Survey, Vegetation clearance
- Estimated Start Date
- 30/01/2023
- Estimated End Date
- 03/02/2023
What we are doing
We will be working along Shaw Lane to clear vegetation and undertake trial hole surveys. The surveys are being undertaken to progress the design of the utilities that need to be diverted at this location.
The works will take place from Monday 30 January to Friday 3 February 2023. To carry out these works safely we will install a temporary closure of Shaw Lane. The closure will be in place from 9.30am to 3.30pm each day.
Access to properties along Shaw Lane will be maintained.