Notice of temporary daytime closure on A4091 northbound near Middleton
Work item: HS2-EW-LM-Ph1-Ar-No-N2-Traf-2-02/10/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Middleton
- Contractor
- LM JV
- Type of works
- Early construction works
- Estimated Start Date
- 08/03/2021
- Estimated End Date
- 27/03/2021
What we are doing
There will be a temporary off-peak daytime road closure on the A4091 northbound, alongside a lane closure on the A4091 southbound in the same area. This closure will allow safe access to our work sites to prepare for future construction works, which include roadside vegetation clearance.