Updated Notice of Lavender Hall Lane closure, Berkswell

Work item: HS2-BBV-25-1155

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire
Location
Berkswell
Worksite Name
Lavender Hall Lane
Contractor
BBV JV
Type of works
Road closure
Estimated Start Date
29/09/2025
Estimated End Date
03/10/2025

What we are doing

The new railway will pass under Lavender Hall Lane Overbridge which is currently in an advanced stage of construction. We are progressing works on the new road realignment which requires significant earthworks, utility and highway alterations to raise the existing road level by 10 metres. These works will be carried out under a long term closure in early 2026.

The prepare for these works we will undertake some vegetation clearance.

We previously communicated that the temporary closure would be from 9am to 3pm. Due to circumstances out of our control the times have been revised from 1pm to 6pm.

From Monday 29 September to Friday 3 October 2025, we will now close the road between 1pm to 6pm.