Notice of temporary lane closures on Faraday Avenue and the A446
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-3-07/12/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Staffordshire, West Midlands
- Location
- Lea Marston
- Contractor
- Balfour Beatty
- Type of works
- Lane closure
- Estimated Start Date
- 12/02/2024
- Estimated End Date
- 22/05/2024
What we are doing
We will be undertaking works to construct the temporary diversion of Faraday Avenue which will enable the construction of Faraday Avenue Underbridge.
These works will require us to close one lane at a time whilst we complete surfacing works and hardening the central reservation before moving traffic onto the new temporary diversion.
To complete these works safely we will install single temporary lane closures on Faraday Avenue and the A446 southbound as follows:
- 12 February to 15 March 2024 between 9.30am to 3.30pm and 8.00pm to 3.00am.
- 8 April to 22 May 2024 between 9.30am to 3.30pm and 8.00pm to 3.00am.
Whilst it is not possible at this stage to define the specific lane closures for each day these will be limited to A446 Southbound and Faraday Avenue.
Please note we have planned the required temporary single lane closures to avoid peak traffic flow periods.
Access will be maintained for pedestrians.