Notice of temporary lane closures on Faraday Avenue, Hams Hall

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-Works-7-23/08/2022

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire
Location
Hams Hall
Contractor
BBV JV
Type of works
Traffic management
Estimated Start Date
14/11/2022
Estimated End Date
10/03/2023

What we are doing

We will be commencing works on the temporary diversion of Faraday Avenue. The temporary road will be constructed on land next to Faraday Avenue. To enable this work to be commenced, we will:
• Create a safe access point
• Construct a haul road
• Complete utility diversions
• Commence piling works

These works will be completed in two phases.
During phase one, we will install a single lane closure on Faraday Avenue (Inbound), for two weeks, between:
• 9:30am to 3.30pm on Monday 14 November to Friday 25 November 2022 (Mon – Fri)

During phase two, we will install a single lane closure (24 hours) on Faraday Avenue, between:
• Monday 9 January to Friday 20 January 2023 (Inbound)
• Monday 23 January to Friday 3 February 2023 (Outbound)
• Monday 6 February to Friday 10 March 2023 (Inbound)

Download information relating to these works