Notice of temporary lane closures on Faraday Avenue, Hams Hall
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-Works-7-23/08/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Hams Hall
- Contractor
- BBV JV
- Type of works
- Traffic management
- Estimated Start Date
- 14/11/2022
- Estimated End Date
- 10/03/2023
What we are doing
We will be commencing works on the temporary diversion of Faraday Avenue. The temporary road will be constructed on land next to Faraday Avenue. To enable this work to be commenced, we will:
• Create a safe access point
• Construct a haul road
• Complete utility diversions
• Commence piling works
These works will be completed in two phases.
During phase one, we will install a single lane closure on Faraday Avenue (Inbound), for two weeks, between:
• 9:30am to 3.30pm on Monday 14 November to Friday 25 November 2022 (Mon – Fri)
During phase two, we will install a single lane closure (24 hours) on Faraday Avenue, between:
• Monday 9 January to Friday 20 January 2023 (Inbound)
• Monday 23 January to Friday 3 February 2023 (Outbound)
• Monday 6 February to Friday 10 March 2023 (Inbound)
Download information relating to these works