Notice of temporary traffic lights, A445 Leicester Lane, Cubbington

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-43-14/09/2022

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire, West Midlands
Location
Cubbington
Contractor
BBV JV
Type of works
Survey, Traffic management
Estimated Start Date
07/11/2022
Estimated End Date
09/11/2022

What we are doing

To progress HS2 works, we will be undertaking surveys on a section of Leicester Lane, Cubbington.
We will need to install two-way temporary traffic lights, to ensure a safe working area while we carry out the surveys. These will be removed once the works are complete.

Two-way temporary traffic lights will be in place from 7 November 2022 to 9 November 2022, between the hours of 9.30am and 3.30pm. The traffic lights will not be in operation outside of these hours.
Our workforce maybe on site one hour before and one hour after to set up and secure our equipment.