Notice of temporary traffic lights on A525 Bar Hill, Madeley
Work item: HS2-EW-BB-Ph2A-Prog-works-26-31/05/2022
Work Item Summary
- Project Phase
- Phase 2a
- Region
- Staffordshire
- Location
- Madeley
- Worksite Name
- A525 Barr Hill Road
- Contractor
- Balfour Beatty
- Type of works
- Early Environmental Works
- Estimated Start Date
- 29/08/2022
- Estimated End Date
- 31/05/2023
What we are doing
As part of our early environmental works, we will establish critical environmental and species relocation sites creating new habitats for local wildlife before any main work starts.
We will be creating various ecological habitats on land to the south of Bar Hill. Once complete, the habitats will be ready to receive sensitive species like Great Crested Newts from other line of route sites.
Before we start to construct the habitat areas, we need to excavate some archaeological trial trenches. These are to help us understand if
there are any archaeological features or natural geological deposits that we need to be aware of before we start any other work. We will use a mechanical excavator to dig the trenches, and to get this excavator in and out of the site safely, we need to install temporary traffic lights on A525 Bar Hill.
We will put the temporary traffic lights in place on Tuesday 29 August and Friday 2 September from 9am to 5pm.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]