Updated notice of temporary traffic lights on B4455, Fosse Way
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-33-20/03/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire, West Midlands
- Location
- Offchurch
- Contractor
- BBV JV
- Type of works
- Emergency repairs
- Estimated Start Date
- 26/04/2023
- Estimated End Date
- 28/04/2023
What we are doing
We will be removing and replacing a damaged signpost on the southside of the roundabout at the Fosse Way and Welsh Road junction.
Due to high traffic volume, to maintain the smooth flow of traffic and to carry out this work safely, we need to install four-way temporary traffic lights at the roundabout during the day.
The works will take place from 17 to 21 April 2023, with the temporary traffic lights operating from 9.30am to 3.30pm, to reduce disruption the traffic, the lights will be switched off during peak hours.
Due to the late delivery of materials this work could not take place between 17 and 21 April, it will now take place between 26 and 28 April from 9.30am to 3.30pm, to reduce disruption the traffic lights will be switched off during peak hours.
Download information relating to these works
- Notice of temporary traffic lights on B4455, Fosse Way
- Updated notice of temporary traffic lights on B4455, Fosse Way
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]