Notice of temporary traffic lights, on Fosse Way, Offchurch.
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-6-13/10/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire, West Midlands
- Location
- Offchurch
- Worksite Name
- Fosse Way
- Contractor
- BBV JV
- Type of works
- Survey, Traffic management
- Estimated Start Date
- 25/10/2022
- Estimated End Date
- 28/10/2022
What we are doing
We will be carrying out drainage surveys on the Fosse Way, Offchurch to support our design process.
To complete the surveys safely we will need to install two-way temporary traffic lights. These will be removed once the works are complete. The traffic lights will be in place 24 hours a day from 25 October to 28 October 2022. Our working hours will be 9.30am to 3.30pm.