Notice of temporary traffic lights, on Fosse Way, Offchurch.

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-28-24/11/2022

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire, West Midlands
Location
Offchurch
Worksite Name
B4455, Fosse Way
Contractor
BBV JV
Type of works
Traffic management
Estimated Start Date
06/02/2023
Estimated End Date
17/02/2023

What we are doing

We will be constructing a plant crossing between the roundabouts at the junctions of Welsh Road and Long Itchington Road.
We will need to install two-way temporary traffic lights, to ensure a safe working area while we install the plant crossing. These will be removed once the works are complete. These traffic lights will be operational from 6 February to 17 February 2023 24 hours per day. Our working hours will be 8am to 6pm Monday to Friday and possibly 8am to 1pm on Saturday.

The plant crossing once operational will remain in place until 2024 to allow construction traffic movement without impacting public journey times and traffic volume to the area. This will be done by installing traffic lights at the crossing to ensure public traffic always has priority.