Notice of temporary traffic lights on Waste Lane, Balsall Common

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-12-15/05/2025

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire
Location
Balsall Common
Worksite Name
Waste Lane
Contractor
BBV JV
Type of works
Traffic management
Estimated Start Date
02/06/2025
Estimated End Date
27/06/2025

What we are doing

To enable the new railway to pass under Waste Lane, the road will have to be realigned over a new bridge before the existing bridge is
demolished.

We need to carry out some preparatory works along the north verge of Waste Lane. To complete these works safely we will be installing
temporary two-way traffic lights.

The works will take place from Monday 2 June to 27 June 2025 and the temporary traffic lights will be on 24/7